Hello All- This is a daily progress report on Century Village construction project:
- Adjustment to traffic light at West Drive/Okee Blvd. seems to have done the trick- no more vehicle backups at West Drive.
- To deter drivers who insist on attempting to exit via Century Boulevard entrance lanes, two additional 'DO NOT ENTER" signs will be placed at Century Boulevard/East Drive.
- Trees and concrete have been removed from property. Sod removal continues. Rough grading work continues.