CENTURY BLVD. CONSTRUCTION PROJECT - LCAM UPDATE

-
DONALD FOSTER
8:35 PM (22 minutes ago)
to Dave, Eva, Dom, David, Stewart, JOHN, Sandra, RKC, Michael, Derek, David, Security, Fausto
-
Good Evening All- Here is daily update on Century Boulevard Construction Project:
-
- Staking for new sidewalk was completed today. 
=

 

- Grading for new sidewalk will begin tomorrow.
-
- Date for installation of irrigation will be determined tomorrow, after onsite meeting with GC.
-
- FPL has confirmed installation of additional LED streetlights to be completed by 11/18.
-
- Platinum Security reports that CV residents continue to move traffic barriers to open up entrance to Borden Street, and they are also driving on the grass swales to access Century Boulevard. Tomorrow, I will ask our General Contractor to order additional temporary fence panels to block off this entrance. Fence panels will extend onto grass swales on either side of Borden Street entrance to deter these dingbats from creating unsafe work site conditions.
-