|
9:14 AM (4 hours ago)
| |||
Tuesday, December 10, 2019
CENTURY BLVD. CONSTRUCTION PROJECT UPDATE - DECEMBER 10, 2019
-
Good Morning All- This is update on the Century Boulevard Construction Project:
- Installation of concrete sidewalk continued today. The bulk of the sidewalk should be poured out by end of day tomorrow, with pouring of drainage flumes and tie-ins to be done last.
- Federal Engineering was on site today to collect concrete sample canisters. DKK Project Manager David Biggs was on site to supervise.
- RKC is installing concrete form boards for the eastern section of sidewalk, and is also making final grading and compaction. DKK will need to check this work at end of day.
- Marc Trudell, RKC Land Development, reports that installation of new fence is scheduled to begin on 12/20- Permit issues will be worked out this week.
- I have instructed Marc to plan on restoring the temporary pedestrian entrance, at north side of Century Boulevard to it's original condition.
Donald
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.